Update

The Second floor of Loso Hall is back online. The network appears to be stable and no further disruption is expected at this time.
Posted Aug 04, 2023 - 11:29 PDT

Update

The entire first Floor of Loso Hall should be back online at this time. We are beginning on the Second floor now.
Posted Aug 04, 2023 - 10:11 PDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 04, 2023 - 08:00 PDT

Scheduled

Network maintenance has been scheduled.

Critical components of the network infrastructure within Loso Hall must be replaced. A complete network outage will occur within the building while the maintenance is performed. Some areas within the building may go offline and come back online at different times during the maintenance window.

Updates will be posted as more information becomes available.
Posted Jul 24, 2023 - 11:18 PDT