Electrical Maintenance

Scheduled Maintenance Report for Eastern Oregon University

Completed

The maintenance has been completed and no disruptions are expected.
Posted Dec 18, 2025 - 09:35 PST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 18, 2025 - 08:00 PST

Scheduled

Facilities will be performing some maintenance on IT-related electrical systems in the Library. The maintenance will begin at 8:00 am on Thursday, December 18, 2025 and should be completed within a couple of hours. We expect all campus IT services to remain operational during this time, but there will be an elevated risk of outage due to the loss of power redundancy.

IT will migrate virtual services and data over to the Ackerman datacenter in preparation for this work.

Updates will be posted as more information becomes available.
Posted Dec 17, 2025 - 09:26 PST
This scheduled maintenance affected: EOU Campus Power.